PIM · Guide

PIM Implementation: How to Roll Out Your PIM System Successfully

apollon Editorial Team · · Reading time approx. 25 minutes

You want to implement a PIM system? Buying the software is the quick part. Whether it actually takes work off your team afterward is decided in the implementation: in the data model, in the interfaces, in the migration, and by the people who work with it every day. This guide shows you every phase in detail, with examples, roles, pitfalls, and an interactive readiness check.

Key takeaways

  • PIM projects rarely fail because of the software, but because of unclear data ownership, a lack of capacity, and IT being brought in too late.
  • The data model is the foundation. Mistakes here affect every interface, every channel, and every translation.
  • Clarify early which system is the leading system for which field. Otherwise ERP, PIM, and online store will overwrite each other.
  • Start with a pilot: one product group, one channel, a measurable result. Then scale.
  • Data quality becomes measurable as soon as you define mandatory attributes per channel.
  • AI noticeably speeds up enrichment and translation, but it requires clean structures and approvals.

What is a PIM implementation?

A PIM implementation (also called PIM rollout or PIM introduction) is the project in which a product information management system is made usable within the company. It includes the data model, workflows, interfaces to ERP, DAM, and online store, the data migration, training, and the go-live. The goal: a central source for all product information that supplies every sales channel.

Product information management (PIM) brings together technical specifications, marketing copy, translations, and media in one place. This guide shows you how to implement a PIM system step by step.

01

Why PIM projects rarely fail because of the software

Talk to teams whose PIM implementation has stalled, and you will rarely hear “The system can’t do that.” Far more often you hear sentences like: “We didn’t know who approves the attributes.” “The ERP interface came three months late.” “Product management had no time alongside day-to-day business.”

A PIM system changes how a company works with its product information. It creates a central source that feeds the online store, marketplaces, catalog, retailer portals, and increasingly AI assistants as well. For this to work, three levels have to fit together:

  • Structure: a data model that reflects your product range and your channels.
  • Technology: interfaces that reliably move data into the PIM and out of it.
  • Organization: clear responsibilities, processes, and people who want to use the system.

The software is the tool. What makes the difference is how well structure, technology, and organization work together.

Most guides concentrate on the organizational level. It is important, and we cover it in detail. But this guide also goes where projects actually lose time and budget: into the data model, the migration, and the integration architecture.

02

What a PIM implementation involves: 7 work packages

PIM implementation, PIM rollout, and PIM introduction all mean the same thing: the path from the signed system decision to the moment when your team, in its day-to-day work, creates and enriches product data and publishes it to the channels exclusively in the PIM. System selection comes before that, ongoing operations after.

What lies in between is more than a software installation. The following diagram shows where a PIM sits in a typical system landscape and which connections are created during implementation.

PIM in the system landscapeSources such as ERP, supplier data, media, and legacy data flow into the PIM. From there, the online store, marketplaces, print, retailer portals, and AI assistants are supplied.SOURCESCHANNELSERPItem no., prices, stockSuppliersBMEcat, Excel, portalsDAM / mediaImages, videos, data sheetsLegacy dataExcel, store back end, CMSPIMData model & classificationWorkflows & approvalsQuality rulesTranslationsChannel viewsOnline storeB2C & B2BMarketplacesAmazon, Otto, Kaufland …Print & catalogCatalog, flipbook, price listRetailers & feedsBMEcat, ETIM, portalsAI assistantsvia API / MCP
Every arrow stands for an interface, a mapping, and a responsibility that has to be clarified during implementation.

Specifically, a complete PIM implementation comprises these seven work packages:

Structure

Data model

Product types, attributes, classification, variants, inheritance, languages.

Organization

Processes & workflows

Who creates, who enriches, who approves? With which quality rules?

Technology

Integration

Connecting ERP, DAM, online store, marketplaces, and suppliers.

Data

Migration

Cleanse existing data, map it, and transfer it in several runs.

Output

Channel views

Mandatory fields, formats, and texts per channel and target market.

People

Roles & training

Permissions, responsibilities, training, key users.

Operations

Go-live & hypercare

Cutover, stabilization, handover to regular operations.

03

PIM implementation in 7 phases: from target vision to regular operations

Every PIM project is different, but the sequence of tasks hardly is. The following seven phases have proven themselves. In practice they overlap; data model, integration, and migration in particular run partly in parallel. But the order of the decisions should be kept: if you build interfaces before the data model is in place, you build them twice.

Phase 0 · Vision

Target vision & business case

Before a single line is configured, you clarify which problem the PIM is supposed to solve and how you will measure success. “Better product data” is not enough. “New items online in 5 days instead of 15” is.

Deliverables

  • Measurable project goals
  • Scope: product ranges, channels, languages
  • Budget and capacity framework

People involved

  • Executive management as sponsor
  • Product management, e-commerce, marketing
  • Head of IT

Key question

  • What will be measurably better in 12 months than it is today?

Pitfall: Goals stay vague, and later no one can decide which requirement takes priority.

Phase 1 · Analysis

As-is analysis & requirements

You record where product data originates today, who maintains it, which systems it lives in, and which channels need what. The most honest source is not process descriptions but the Excel lists your team actually works with.

Deliverables

  • Inventory of data sources
  • As-is process map
  • Prioritized requirements (must/should/could)

People involved

  • Key users from all business departments
  • IT / system owners
  • Implementation partner

Key question

  • Where is the most time lost today?

Pitfall: All wishes end up in the requirements specification with equal priority. Without prioritization, the scope grows uncontrolled.

Phase 2 · Structure

Data model & data governance

The most important phase. You define product types, attribute groups, classifications, variant logic, and inheritance, and determine who is responsible for which data. Details in the data model chapter.

Deliverables

  • Data model (business and technical)
  • Attribute catalog with definitions
  • Data ownership matrix

People involved

  • Product management (business lead)
  • E-commerce and marketing
  • Partner (methodology)

Key question

  • Can every channel requirement be served from this model?

Pitfall: The old Excel format is rebuilt 1:1 instead of designing a model for the future channels.

Phase 3 · Technology

Integration architecture

You define which systems exchange data in which direction, at what frequency, and by which route. IT must be in the project with fixed capacity by now at the latest, ideally from phase 1.

Deliverables

  • Interface concept
  • Field mappings per system
  • Error handling and monitoring concept

People involved

  • IT, ERP and online store owners
  • External service providers for the surrounding systems
  • Partner (architecture)

Key question

  • What happens if an interface fails at night?

Pitfall: The effort on the side of the surrounding systems is not planned for. The online store agency only learns about the new data format shortly before go-live.

Phase 4 · Data

Migration & data cleansing

Existing data is analyzed, cleansed, mapped to the new model, and transferred in several test runs. This phase is almost always underestimated. More on this in the migration chapter.

Deliverables

  • Data profiling report
  • Mapping and cleansing rules
  • At least two trial migrations

People involved

  • Data stewards from the business departments
  • IT / database know-how
  • Partner (migration tools)

Key question

  • Which data do we really need in the new system?

Pitfall: “We’ll clean that up in the new system.” In practice that rarely happens, and the legacy baggage stays.

Phase 5 · Pilot

Pilot, testing & rollout

A manageable product group runs completely through the new system all the way into one channel. This is how you test the data model, workflows, and interfaces under real conditions. After that, further product ranges, languages, and channels follow in waves.

Deliverables

  • Pilot live in one channel
  • Acceptance tests with the business departments
  • Rollout plan in waves

People involved

  • Key users as testers and multipliers
  • Entire project team
  • Channel owners

Key question

  • Would the team voluntarily work in the PIM instead of in Excel?

Pitfall: The pilot is scoped too large and loses its function as a way to learn fast.

Phase 6 · Operations

Go-live, hypercare & regular operations

After the cutover comes a phase of intensive support in which questions are answered quickly and teething problems are fixed. After that, the internal team takes over operations and further development.

Deliverables

  • Cutover plan with fallback option
  • Shutdown of the legacy systems
  • Operating and support model

People involved

  • Project team and partner
  • Support / service desk
  • Product owner for further development

Key question

  • Who decides on new attributes from tomorrow on?

Pitfall: Legacy systems keep running in parallel. If you have two sources, you have none.

04

The PIM data model: the foundation nobody sees

The data model defines how product information is structured in the PIM. It is invisible to customers, but it determines whether your online store can offer clean filters, whether marketplace feeds go through without rework, and whether a new language is available in days or months.

The five building blocks of a robust model

  1. Product types and attribute groups. A cordless drill/driver needs different attributes than a work glove. Product types bundle the matching attributes, and attribute groups organize them for maintenance (technical, logistics, marketing, legal).
  2. Classification. Internal product groups for the organization, standards such as ECLASS, ETIM, or GS1 GPC for exchanging data with retail and industry, and separate navigation trees per online store. A good model keeps these hierarchies separate instead of mixing them.
  3. Variants and inheritance. Shared information is maintained once on the master and inherited by the variants. Only what differs, such as color, size, or voltage, is maintained at variant level.
  4. Multilingualism and localization. Which attributes are language-dependent, which are country-dependent (such as plug type or approvals), and which are universal?
  5. Channel views. Every channel has its own mandatory fields, character limits, and formats. Instead of duplicating data per channel, you define views and rules on the same master data.

Example: where each piece of information is maintained

This is what the distribution looks like for a cordless drill/driver with three variants. The effect: an error in the marketing copy is corrected once and is fixed in all variants and channels.

AttributeLevelLanguage-dependentExample valueMandatory for
Product nameMasteryesCordless drill/driver BS 18all channels
Marketing copyMasteryesCompact, powerful, for overhead installation work …Online store, marketplaces
Max. torqueMasterno60 NmOnline store, ETIM feed
Battery capacityVariantno2.0 Ah · 4.0 Ah · without batteryall channels
GTINVariantno4006…Marketplaces, retailers
Weight incl. batteryVariantno1.4 kgOnline store, logistics
Safety informationMasteryesInformation in accordance with the operating instructionsall channels (GPSR)
Bullet pointsChannel viewyes5 × max. 200 charactersAmazon
ETIM classMasternoEC…Specialist retailers

Practical tip: For every attribute, write down a definition, a data type, permitted values, a unit, and a responsible role. This attribute catalog is the most important document of the entire project. It prevents “color” from meaning “anthracite” in one department and “RAL 7016” in another.

Better a few cleanly defined attributes with value lists than many free-text fields. Free text is quick to set up, but it cannot be filtered, cannot be translated via a value list, and can hardly be checked automatically.

05

PIM, ERP, DAM, and online store: which system is the leading system?

One of the most common causes of data chaos after go-live: two systems maintain the same field, and the interface overwrites at night what was corrected during the day. So define exactly one leading system (system of record) for every data group. All others only read.

Data groupERPPIMDAMOnline store
Item number, basic dataleadsreads–reads
Prices, stock levelsleads––reads
Technical specifications–leads–reads
Marketing copy, SEO–leads–reads
Translations–leads–reads
Images, videos, documents–linkedleadsreads
Store navigation, categories–leads–reads
Logistics data (dimensions, weight)leadsreads–reads

This distribution is a typical pattern, not a rule. In some companies the PIM is also the leading system for logistics data, for example when it comes from suppliers. What matters is that the matrix exists, is signed by all system owners, and is reflected in the interfaces.

When PIM and DAM come together in one system, as in the OMN platform, an entire interface is eliminated and with it a typical source of errors: images and product data are linked from the start.

06

Making product data quality measurable

“Our data is bad” is not a project goal. “92% of items meet all mandatory attributes for the online store” is. Data quality becomes manageable as soon as you break it down into dimensions and define rules per channel.

Dimension 1

Completeness

Are all mandatory attributes for channel X and language Y filled in?

Dimension 2

Accuracy

Are values, units, and formats correct? Is the weight within a plausible range?

Dimension 3

Consistency

Is “stainless steel” spelled the same way and classified the same way everywhere?

Dimension 4

Timeliness

When was the record last reviewed? Are discontinued items flagged?

Dimension 5

Uniqueness

Are there duplicates among GTINs, item numbers, or images?

Building quality gates into the workflow

Data quality is most effective when it is not checked after the fact but enforced in the process. An item only moves to the status “ready for online store” once all mandatory fields for the online store are filled in and the plausibility rules are met. That way, no more half-finished product pages are created.

Tip for the project start: Measure the completeness of your most important channels as early as phase 1. These baseline values are the basis for your business case and make progress visible after go-live.

07

PIM data migration: the underestimated heavy lift

Data migration is rarely technically difficult. It becomes laborious because it forces decisions that have been put off for years: Which of the three spellings is correct? Who knows what “special attribute 4” means? Do we still need the 8,000 discontinued items?

Six steps to a clean migration

  1. Take inventory. Record all sources: ERP, Excel lists, store back end, supplier files, network drives with images.
  2. Profile. Analyze automatically how complete, how consistent, and how full of duplicates the data is. The results are almost always surprising.
  3. Sort out. Discontinued items, unused fields, and duplicate attributes stay out. Every record that is not migrated is one less that has to be maintained.
  4. Cleanse. Decide what gets cleansed in the source, what by rule during the transfer, and what later in the PIM. Rule of thumb: fix structural errors before the migration, do content enrichment afterward in the PIM.
  5. Map and run trial migrations. Field-by-field mapping to the new model, then at least two complete test runs. Every run uncovers special cases that nobody thought of the first time.
  6. Cutover. Freezing maintenance of the legacy data, final transfer of the deltas, validation, switching over the interfaces. With a documented plan and a defined fallback option.

Plan realistically: In many projects, the data work (cleansing, mapping, enrichment) accounts for a larger share of the total effort than the system configuration. Plan fixed capacity for it in the business departments, not “on the side.”

AI-supported tools now help noticeably here: they detect duplicates, suggest classifications, extract specifications from free text and data sheets, and standardize spellings. The business decision remains with people, but the tedious manual work shrinks.

08

PIM interfaces: connecting ERP, online store, and marketplaces

A PIM only unfolds its value through the systems it supplies. At the same time, interfaces are the most common reason for delays, because several teams and often external service providers have to work together here.

Four integration patterns and when they fit

PatternHow it worksSuitable forWatch out for
File-based (batch)Export/import of CSV, XML, BMEcat at fixed intervalsSuppliers, retailers, older ERP systems, printLatency, error logs, full export vs. delta
API (REST/GraphQL)Systems query specific data or write itOnline stores, headless front ends, appsLoad peaks, authentication, versioning
Event-basedA change in the PIM triggers a message, subscribers reactNear-real-time channels, many recipientsSequence, retries in case of errors
Syndication / feedsChannel-specific preparation and deliveryMarketplaces, price comparison portals, data poolsChannel rules change constantly

Ten questions every interface concept has to answer

  1. Which data flows in which direction?
  2. Which system leads for each field (see ownership matrix)?
  3. How often is data synchronized: in real time, hourly, nightly?
  4. Full or delta transfer?
  5. How are IDs mapped between systems?
  6. What happens in case of errors: abort, partial transfer, retry?
  7. Who is notified in case of errors, and how quickly?
  8. How is the interface tested, including with mass data?
  9. Who has to rebuild something on the other side, and is that budgeted?
  10. How does the interface stay stable when both systems are updated?

New channel: AI assistants. More and more purchase decisions begin in chat assistants and AI search. Open standards such as the Model Context Protocol (MCP) make it possible to provide product data directly to AI applications. At apollon, the OMN MCP Server in OMN 7 provides exactly this connection. Include this channel in your architecture planning, even if you do not use it right away.

09

Approaches to PIM implementation: full service, in-house, or hybrid

Besides choosing the right PIM software, two decisions shape the project: How do you divide responsibility between the internal team and the partner? And do you roll out everything at once or step by step?

Responsibility: full service, in-house, or hybrid

CriterionFull serviceIn-houseHybrid
PrinciplePartner implements, team supplies inputInternal team implementsPartner leads on methodology, team takes over step by step
Internal capacitylowhighmedium
External costshighlowmedium
Know-how in-house afterwardlowhighhigh
Project riskmediumhighlow
Fits when …Time pressure is high, internal capacity is scarce, standard requirementsan experienced PIM team is in place, system change rather than first projectFirst PIM project, operations are to run internally

Pace: big bang or step by step

With a big bang, all product ranges, channels, and languages go live on one fixed date. This saves running two systems in parallel but concentrates all risks on one day. With a step-by-step rollout, you start with a pilot and expand in waves.

For most companies, the step-by-step route is the better choice. It delivers visible results after a few weeks, the team learns on the real system, and corrections to the data model are still inexpensive early on. A good pilot has three characteristics: it is small enough for quick results, representative enough for real insights, and it goes into a channel where the benefit is measurable.

A fast start with a standard: Preconfigured packages such as the OMN Accelerator come with a proven basic model, workflows, and roles. You do not start with an empty system but adapt a proven framework. This shortens phases 2 and 5 in particular.

10

The PIM project team: roles and responsibilities

“Product management, marketing, and IT belong on the team” is correct, but too coarse. Successful projects staff roles, not departments. One person can have several roles, but every role needs a name and reserved time.

RoleTaskTypical backgroundShare of time in the project
SponsorApproves goals and budget, decides in case of conflictsExecutive management, division managementlow, but reliable
Product ownerPrioritizes requirements, is accountable for the resultE-commerce, product managementhigh, ideally 50% or more
Project managementPlan, resources, risks, communicationinternal or partnerhigh
Data ownerBusiness responsibility for a data domainProduct management, marketing, engineeringmedium
Data stewardMaintains the attribute catalog, safeguards quality in day-to-day workBusiness department with an affinity for datahigh during migration
Integration ownersInterfaces, mappings, monitoringIT, ERP teammedium to high in phases 3 and 4
Key usersTest, give feedback, train colleaguesall departments that maintain datamedium in phase 5
Implementation partnerMethodology, system knowledge, configuration, best practicesVendor or service providerdepending on the implementation approach

Capacity is a commitment, not a hope. If the product owner is supposed to keep the full day-to-day workload alongside the project, the project will slip. Before the project starts, clarify in writing who is released from regular duties or who covers for them.

11

Change management in the PIM project: adoption and training

A PIM changes habits. Anyone who has worked with a personal Excel list for years is also giving up a bit of control. That is why adoption does not come from announcements but from involvement and noticeable relief.

What works in practice

  • Involve people early: Key users help shape the data model and workflows. Those who helped decide will defend the result.
  • Show the benefit for each individual: not “better data quality,” but “You no longer have to copy texts into three systems.”
  • Train with your own data: training in a test environment with real products instead of sample data.
  • Train by role: The translator needs different functions than the product manager. Short, targeted sessions instead of one full-day training for everyone.
  • Timing: Training shortly before people start using the system themselves. What was learned three months before go-live is forgotten by go-live.
  • Train the trainer: Key users become the contact persons in their teams. This scales better than central training and reduces support requests.
  • Make successes visible: Share the first KPIs from the pilot within the company.

12

AI in PIM implementation: where it really helps today

AI has changed the economics of PIM projects. Tasks that used to mean weeks of tedious manual work now go much faster. At the same time, AI amplifies what is there. On a clean data model it delivers excellent results; on a chaotic one it produces chaos faster.

Migration

Extract specifications

Convert technical values from free text and PDF data sheets into structured attributes.

Structure

Classify

Suggestions for product groups and ECLASS or ETIM classes based on existing data.

Content

Create texts

Generate product descriptions and bullet points per channel from structured attributes.

Markets

Translate

New languages in days instead of months, with the company’s glossary and terminology.

Media

Image variants

Automatically create cutouts, formats, and variants for different channels.

Quality

Check

Detect contradictions, implausible values, and duplicates before they are published.

Human in the loop as the standard

For product data that is legally relevant or influences purchase decisions, AI results should be reviewed by people before publication. In OMN 7, the AI assistant OMN Companion works exactly this way: it creates texts, translations, and image variants, and nothing is saved until a human has approved it. An example from practice: EFALOCK manages around 15,000 items and 20,000 media files in one system and has translated the content into three languages with AI support.

For project planning, this means: Plan AI functions into the workflows from the start (Who reviews? By which criteria? How is it documented?) instead of bolting them on afterward. And think the other way around too: clean, structured product data in the PIM is the prerequisite for AI search and assistants to present your products correctly.

13

GPSR, accessibility, Digital Product Passport: regulations in the PIM

Product data has long been more than just marketing. Several EU regulations require information that has to be available in structured form and published across channels. If you take them into account in the data model now, you save yourself an expensive rebuild later.

Since December 2024

Product safety (GPSR)

The EU General Product Safety Regulation (GPSR) also requires online offers to include, among other things, manufacturer details, a product identifier, an image, and warnings and safety information. These fields belong in the model as mandatory attributes.

Since June 2025

Accessibility (EAA)

The German Accessibility Strengthening Act (BFSG) affects many online stores. For product data this means, among other things: alternative texts for images and well-structured, understandable information.

From 2027, step by step

Digital Product Passport (DPP)

With the Ecodesign Regulation (ESPR) and the Batteries Regulation, digital product passports are coming, starting with certain batteries. Further product groups will follow via delegated acts. Data on material, origin, repairability, and recycling will then be needed in structured form.

A PIM is the natural place for this information because it is already the central, cross-channel source. In phase 2, check which regulations apply to your product range and set up the corresponding attribute groups from the start. The specific obligations depend on the product category and your role in the market; if in doubt, clarify them with your legal department.

14

How long does a PIM implementation take?

The honest answer is: it depends. It is more helpful to know on what. The following scenarios are rough guide values for the time until the first productive channel with the core product range. They do not replace project planning.

ScenarioTypical characteristicsGuide value
Focused startPreconfigured standard, one to two channels, few interfaces, manageable data volumea few weeks to approx. 3 months
Mid-sized projectSeveral product ranges, ERP + online store + marketplaces, 2 to 5 languages, migration from several sourcesapprox. 4 to 9 months
Complex initiativeMany countries and legal entities, numerous channels and surrounding systems, extensive variant modelapprox. 9 to 18 months and longer, in waves

What speeds projects up

  • Clear, prioritized goals and a product owner with decision-making authority
  • Preconfigured standard instead of custom development
  • Data cleansing starts in parallel with the concept phase
  • Pilot instead of big bang
  • PIM and DAM in one platform: one interface less

What slows projects down

  • Missing decisions, especially on the data model
  • Capacity that exists only on paper
  • Late involvement of IT and the external service providers for the surrounding systems
  • Data cleansing that is supposed to happen only after go-live
  • Scope extensions during the project without reprioritization

15

What does a PIM implementation cost? Costs and business case

What does a PIM system cost? Flat price figures are of little help in PIM projects because product range, channels, and system landscape differ too much. What does help: knowing the cost blocks and looking at them over three to five years as total cost of ownership (TCO).

Cost blockWhat it includesOften underestimated?
License / subscriptionUse of the software, depending on the model by users, modules, or data volumerarely
ImplementationConcept, configuration, project management, training by the partnersometimes
InterfacesDevelopment in the PIM and on the side of the surrounding systems (ERP, online store, agencies)often
Data workCleansing, mapping, enrichment, translation, media preparationoften
Internal effortTime of product owner, business departments, IT, and key usersalmost always
Operations & hostingData center or on-premises, updates, supportrarely
Further developmentNew channels, languages, attributes, AI functionssometimes

The benefit side of the business case

The costs are offset by effects that you should back up with baseline values as early as phase 0:

  • Time to market: How many days pass today from creating an item to its availability in the online store? Every day earlier means revenue, especially for seasonal goods.
  • Maintenance effort: How many hours go into copy and paste between systems, Excel reconciliations, and follow-up questions?
  • New channels and markets: What does an additional marketplace or a new language cost today, and what will it cost in the future?
  • Returns and inquiries: Complete, correct product information reduces product-related returns and support requests.
  • Risk: Missing mandatory information can result in legal warnings and marketplace suspensions.

A simple calculation to start with: number of new items per year × maintenance time saved per item × hourly rate. In many companies, this one figure alone covers a considerable part of the investment.

16

PIM KPIs: measuring success after go-live

Go-live is not the goal but the starting point. These KPIs show whether your PIM is actually having an effect. Collect them before the project, after three months, and regularly after that.

KPIWhat it showsHow you measure it
Time to marketSpeed of item creationDays from creation to status “online”
Completeness per channelData quality from the channel’s perspectiveShare of items with all mandatory fields
Manual reworkProcess efficiencyCorrections after approval per month
Feed error rateIntegration qualityRejected items per marketplace
Languages & channelsReachNumber of actively served channels and languages
UsageAdoption in the teamActive users, remaining Excel shadow lists

17

12 typical mistakes in PIM implementation

MistakeConsequenceRemedy
Vague goalsNo basis for prioritizationMeasurable goals in phase 0, approved by the sponsor
Rebuilding Excel 1:1Old weaknesses in the new systemDerive the data model from channel requirements
No ownership matrixSystems overwrite each otherOne leading system per data group
IT involved too lateInterfaces delay the go-liveIT with fixed capacity from phase 1
Surrounding systems forgottenOnline store or agency not preparedInform service providers early and budget for them
Data quality underestimatedMigration takes many times longerProfiling in phase 1, start cleansing in parallel
Migrating everythingLegacy baggage in the new systemSort out consistently
Capacity only on paperProject keeps slippingAgree in writing on release from regular duties
Big bang without needAll risks on one dayPilot and rollout in waves
Training too earlyKnowledge is gone by go-liveRole-based, shortly before use
Legacy systems keep runningTwo truths, no adoptionSet and communicate a shutdown date
No operating modelData quality declines after the projectAppoint product owner and data stewards permanently

18

PIM readiness check: are you ready for a PIM system?

Answer ten questions honestly. The result shows you where you should still take action before the project starts. Your answers stay in your browser.

1. Are there measurable goals for the PIM project?e.g., time to market, completeness, new channels
2. Has a product owner with decision-making authority been appointed?and does this person have time reserved for it?
3. Do you know which systems and files hold your product data today?including personal Excel lists
4. Is it clear which system is the leading system for which data?ERP, PIM, DAM, online store
5. Do you know the mandatory fields of your most important channels?online store, marketplaces, retailers, print
6. Is IT scheduled with fixed capacity?including service providers for the surrounding systems
7. Have you already analyzed the quality of your existing data?completeness, duplicates, spellings
8. Is there a suitable pilot area?one product group and one channel with measurable benefit
9. Are the regulatory requirements for your product range known?e.g., GPSR, accessibility, Digital Product Passport
10. Is it settled who takes care of data quality after go-live?data stewards, operating model

0/20

Answer the questions to see your result

For each question, you get 2 points for “Yes,” 1 point for “Partly,” and 0 points for “No.”

The result is calculated in your browser. JavaScript needs to be enabled for this.

19

Checklist for your PIM implementation

Before the start

  • Measurable goals and scope defined
  • Sponsor and product owner appointed
  • Capacity committed in writing
  • Implementation approach decided
  • Baseline values for KPIs collected

Concept

  • Data sources inventoried and profiled
  • Data model and attribute catalog agreed
  • Ownership matrix signed
  • Regulatory mandatory fields taken into account
  • Interface concept incl. error handling

Execution

  • Data cleansing runs in parallel
  • At least two trial migrations
  • Pilot live with one channel
  • Role-based training shortly before use
  • AI workflows with approvals defined

Go-live & operations

  • Cutover plan with fallback option
  • Shutdown date for the legacy systems
  • Hypercare phase planned
  • Operating model and data stewards appointed
  • KPI review scheduled after three months

For day-to-day project work, you will find the steps with testable requirements and test cases in the article PIM Implementation: Project Plan, Requirements and Checklist.

20

Frequently asked questions about PIM implementation

What is a PIM implementation?

A PIM implementation, also called a PIM rollout or PIM introduction, is the project in which a product information management system is made usable: data model, workflows, interfaces to ERP, DAM, and online store, data migration, training, and go-live. The goal is a central source for all product information that supplies every sales channel.

When is a PIM system worth it?

A PIM system pays off as soon as product data is maintained in several systems or Excel lists, several channels or languages are served, many variants exist, or new items take too long to get published. What matters is less the number of items than the complexity that comes from product range, channels, and markets.

How long does a PIM implementation take?

A focused start with a preconfigured standard is in production within a few weeks to around three months. Mid-sized projects with several connected systems typically take four to nine months, international initiatives with many countries and channels a year or more. The biggest factors are data quality, the number of interfaces, and the availability of your team.

What does a PIM implementation cost?

The costs are made up of license or subscription, implementation services, internal effort, data work, interfaces, and operations and further development. They can only be assessed reliably as total costs over three to five years, weighed against benefits such as a shorter time to market and less manual maintenance.

Do I need an implementation partner?

Not necessarily, but in most cases it makes sense. A hybrid approach has proven itself: the partner contributes methodology and system knowledge for data model, architecture, and rollout, while your team gradually takes over responsibility and operations.

What is the difference between PIM selection, PIM implementation, and PIM operations?

Selection clarifies which system fits. Implementation makes it usable: data model, workflows, interfaces, migration, training, and go-live. Operations then take care of data quality, further development, and new channels.

Should you migrate all product data to the new PIM?

No. Discontinued items, duplicate attributes, and unused fields should be sorted out before the migration. A migration is the best opportunity to get rid of legacy baggage instead of carrying it into a new system.

What role does AI play in a PIM implementation?

AI significantly speeds up enrichment, translation, classification, and data cleansing. However, it requires a clean data model and clear approval processes. A human-in-the-loop approach, in which people review and approve AI suggestions, has proven itself.

Big bang or step-by-step rollout?

In most cases step by step: first a pilot with one product group and one channel, then further product ranges, languages, and channels. This lowers the risk and delivers measurable benefits early.

How do I know that the PIM implementation was successful?

By measurable KPIs: time to market for new items, completeness per channel, share of manual rework, error rate in marketplace feeds, number of channels and languages served, and actual use by the business departments.